On the morning of March 12th, the newly-built production line of the fifth foundry of China National Heavy Duty Engine Division was officially put into production. After 28 days of hard work, the foundry center completed the installation and commissioning of the equipment in advance and completed a successful test, with the first furnace hot metal and the first box. The success of the trial production of ductile iron axle shell castings indicates that the axle shell expansion project has been successfully put to a full stop. The third-stage bridge shell expansion project of the Foundry Center is one of the important projects of the group company. With the increasing demand for ductile iron axle housings, the production capacity of the original axle housing production line has been unable to meet the demand. In order to meet the heavy demand in the heavy-duty automotive market, speed up the debugging of the resin sand molding line, and quickly achieve the goal of increasing production. The leaders of the engine department and foundry center have held several special meetings to coordinate the work of the bridge shell expansion project and coordinate the work. The detailed project installation plan requires the installation of the manufacturer's dump plan. Each phase of the work must be completed within a certain period of time. In order to grab time and grab deadlines, the team leader of the project team has repeatedly requested the goods from the manufacturer. In terms of logistics service work, the installation company is given a full range of services and cooperation to ensure the installation work 24 hours a day. The leaders of the center have in-depth production sites, coordinate and solve the difficult problems of constraining the advancement of the bridge-and-shell expansion project, and require various functional departments to cooperate closely. The workshop has set up a commando team to perform on-site supervision of equipment installation quality in equipment installation and commissioning to reduce hidden dangers in equipment installation and commissioning. At the same time, the new employees are trained to take the big classes and on-site teaching in the field. The workshop technicians and the team leader explain the structure, performance, and principles of the equipment, and implement one-on-one links for all kinds of production-prone problems. Training until you can master it. The workshop leaders and technical personnel implement a 24-hour shift system, discuss in a timely manner various problems that arise during the installation and commissioning process, coordinate the progress of each process, and ensure that equipment installation is performed in an orderly manner. Lab Scale Jet Mill,Lab Classifying Jet Mill,Diamond Classifying Jet Mill,Rare Earth Polishing Classifying Jet Mill Mianyang Liuneng Powder Equipment Co., Ltd , https://www.lnpepowder.com